Loop Engineering were appointed to deliver stage 2 design for this 250 apartment, and 4 retail unit development. The plot is part of the wider Brent Cross town redevelopment and as such already has planning approval subject to a Reserved Matters Application (RMA). As part of this RMA we produced an energy and sustainability statement, including BREEAM, SAP and SBEM analysis.
To mitigate the use of refrigerant, a global warming contributor, the apartments have been designed to not include active comfort cooling. We developed an in-depth overheating risk analysis to ensure the apartments would remain comfortable throughout the year and into the future. Within the analysis we included passive cooling design proposal.
Heating is provided from the district heating system. Heating and hot water to the apartments is provided by HIUs. Detailed acoustic and overheating studies were undertaken to mitigate the effects of noise whilst limiting overheating.
We have used Revit 2020 to produce a comprehensive services model that eases and speeds up the installation on site bringing tangible benefits to the contractors and consequently, to the developer.
To mitigate the use of refrigerant, a global warming contributor, the apartments have been designed to not include active comfort cooling. We developed an in-depth overheating risk analysis to ensure the apartments would remain comfortable throughout the year and into the future. Within the analysis we included passive cooling design proposal.
Heating is provided from the district heating system. Heating and hot water to the apartments is provided by HIUs. Detailed acoustic and overheating studies were undertaken to mitigate the effects of noise whilst limiting overheating.
We have used Revit 2020 to produce a comprehensive services model that eases and speeds up the installation on site bringing tangible benefits to the contractors and consequently, to the developer.

Works
Included
Stage 2 MEP design
Overheating risk analysis
Detailed acoustic study
Energy and sustainability statement including BREEAM, SAP and SBEM analysis
Overheating risk analysis
Detailed acoustic study
Energy and sustainability statement including BREEAM, SAP and SBEM analysis
Project
Summary
LOCATIONBrent Cross Town, London, United Kingdom
CLIENTArgent Related
SURFACE271 apartments, 4 retail units, gym